1 / 25

1. Commonly used material for water mains is:

2 / 25

2. Septic tank is designed on the basis of sludge storage of:

3 / 25

3. The expansion joints are provided if the length of the concrete exceeds:

4 / 25

4. Most important step toward damp proofing of a wall is to find out:

5 / 25

5. The strength of a structure in working stress method of analysis is assessed with respect to:

6 / 25

6. Three point problem in plotting of survey is solved by:

7 / 25

7. The fitting used to supply water in service pipe from main pipe is known as:

8 / 25

8. The maximum allowable super elevation in plain rolling terrain is:

9 / 25

9. Curing of concrete is keeping its exposed surface:

10 / 25

10. Codes used in Nepal for building construction/design is:

11 / 25

11. The excavation expending 1.5 m in width and 10 sq.m. in plan area with a depth not exceeding 30 cm, is termed as:

12 / 25

12. In water bound macadam roads, binding material used is :

13 / 25

13. Minimum radius of horizontal curve in hill roads is:

14 / 25

14. Accurate method of discharges measurement from a source of stream is:

15 / 25

15. A passage for the flow of surplus or waste water in a weir or irrigation system is known as:

16 / 25

16. The maximum pressure which a soil can carry without shear failure, is called

17 / 25

17. The compression resulting from a long term static load and consequent escape of pore water, is known as

18 / 25

18. The property of a material by which it can be drawn to a smaller section, due to tension, is called

19 / 25

19. When loads are applied proportionately to a frame structure containing its members in one plane, the structure is called

20 / 25

20. Bending moment at any section in a conjugate beam gives in the actual beam

21 / 25

21. In direct method of contouring, the process of locating or identifying points lying on a contour is called

22 / 25

22. In a rapid sand filter, air binding is caused due to excessive

23 / 25

23. The process of filling hollow spaces of walls before plastering, is known

24 / 25

24. The type of roof which slopes in two directions with a break in the slope on each side is known as

25 / 25

25. Efflorescence in cement is caused due to an excess of

Your score is

The average score is 59%