65

Estimating & Costing Chapter Wise McQ Test of 25 Question #6

Estimating & Costing Chapter Wise McQ Test of 25 Question for PSC, NEC, UPSC, SSC and Many more.

1 / 25

1. How many bricks are there in 1 square metre?

2 / 25

2. No of hollow blocks of size 400*200*100 mm in 1 cube of volume

3 / 25

3. In analysis of rate the quantity of dry mortar for 10 cubic metre brick work is taken as

4 / 25

4. In analysis of rate the quantity of dry mortar for 10 cubic metre brick work is taken as

5 / 25

5. Process of finding rate for unit item of work is called

6 / 25

6. The process of calculating amount of materials, labors, equipment for a unit of work together with overhead and profit for the contractor is

7 / 25

7. Generally, cost for small tools and plants is taken

8 / 25

8. For big work or project a percentage of………….. to……….. of the estimated cost is provided in the estimate for the purchase of tools and plants required for the work.

9 / 25

9. Contractor’s overhead and profit is added in

10 / 25

10. Cost of water required for construction of a structure is

11 / 25

11. The approximate cost of the complete labour as a percentage of the total cost of the building is

12 / 25

12. The ratio of cost of labour to the total cost of the building is

13 / 25

13. The following document contains detailed description of all items of work excluding their quantities, along with the current rates:

14 / 25

14. A document containing detailed description of all the items of work (but their quantities are not mentioned) together with their current rates is called

15 / 25

15. A document containing detailed description of all the items of work, without their quantities, together with their current rates is called

16 / 25

16. VAT stands for

17 / 25

17. The percentage of value added tax included in the government rate analysis norms is

18 / 25

18. BoQ consists of

19 / 25

19. Bill of quantities is prepared based on

20 / 25

20. Rate column of BoQ is filled by contractor in

21 / 25

21. In case of discrepancy between rate in words and figures

22 / 25

22. Contractor’s overhead is taken as

23 / 25

23. Contractor’s overhead and profit is taken as

24 / 25

24. In analysis of rates contractor profit is taken at the rate of

25 / 25

25. Which of the following is general overhead or direct expenses

Your score is

The average score is 57%

0%

Exit

Show CommentsClose Comments

Leave a comment