139

Estimating & Costing Chapter Wise McQ Test of 25 Question #11

Estimating & Costing Chapter Wise McQ Test of 25 Question for PSC, NEC, UPSC, SSC and Many more.

1 / 25

1. Which of the following is useful area of building for living purpose?

2 / 25

2. The useful part of livable area of a building is known as

3 / 25

3. Carpet area does not include

4 / 25

4. Carpet area does not include the area of

5 / 25

5. Which is largest area in following areas of building?

6 / 25

6. The plan of a building is in the form of a rectangle with centre line dimension of outer wall is 9.7m*14.7m. Thickness of wall in superstructure is 0.30 m. Then its plinth area is

7 / 25

7. The plan of a building is in the form of a rectangle with centre line dimension of outer wall is 9.7m*14.7m. Thickness of wall in superstructure is 0.30 m. Then its plinth area is

8 / 25

8. The covered area of a proposed building is 150m². It includes a rear courtyard of 5m*4m. If theprevailing plinth area rate for similar building is Rs. 1250/m². What is its cost.

9 / 25

9. The preliminary or approximate estimate is prepared based on the

10 / 25

10. Which of the following is very rough estimate?

11 / 25

11. Preliminary estimate is prepared on the basis of

12 / 25

12. What is required for preliminary studies of various aspects of a work or project?

13 / 25

13. Approximate cost of a hostel building for 100 students @Rs.10000/- per student works out as

14 / 25

14. Per kilometre basis depending on the nature of road, for 10 km of a state highway approx. cost @ Rs. 50000/- per 1 km works out as

15 / 25

15. Estimate expected to be least accurate is

16 / 25

16. _________ is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.

17 / 25

17. Plinth area estimate is mostly used fo

18 / 25

18. The approximate cost of building cubic content (volume)of 400 cum @ rs. 180 per cum comes to be

19 / 25

19. Which of the following is most accurate estimate?

20 / 25

20. Estimate expected to be least accurate is

21 / 25

21. The most reliable estimate is

22 / 25

22. Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds

23 / 25

23. A revised estimate is usually prepared when the original estimate has exceeded by more than

24 / 25

24. When the original sanctioned estimate is exceeded by more than 5%, in the circumstances which estimate is required?

25 / 25

25. When additional items are added ……………. is prepared.

Your score is

The average score is 55%

0%

Exit

Show CommentsClose Comments