66 Estimating & Costing Chapter Wise McQ Test of 25 Question #10 Estimating & Costing Chapter Wise McQ Test of 25 Question for PSC, NEC, UPSC, SSC and Many more. 1 / 25 1. Centre line length of wall is A. out to out dimension minus full width of wall at each junction. B. into in dimension plus full width of wall at each junction. C. out to out dimension minus half width of wall at each junction D. into in dimension minus half width of wall at each junction. 2 / 25 2. Centre line method is specially adopted for estimating A. circular building B. hexagonal building C. other geometrical shaped building D. all of the above 3 / 25 3. The ‘centre line method’ is specially adopted for estimating the ………… A. circular buildings B. hexagonal buildings C. circular, hexagonal and other geometric shapes D. none of above 4 / 25 4. While estimating building having internal walls with different thickness, the referral method of estimation is A. long- short wall method B. centre line method C. partly centre line and partly cross wall method D. all of the above 5 / 25 5. In crossing wall method, length for inner wall is A. Centre line length minus half width of wall at each junction. B. out to out length of wall minus width of wall at each junction. C. into in length of wall D. all of the above 6 / 25 6. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and A. breadth of the wall B. half breadth of wall on each side C. one fourth breadth of wall on each side D. None of these 7 / 25 7. The cross-sections for a highway is taken at A. right angle to the centre line B. 30 metres apart C. the starting end points of the curves D. All of the above 8 / 25 8. If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is A. B + d + Sd B. Bd + Sd² C. B x d – Sd^1/2 D. 1 /2 (Bd + Sd² ) 9 / 25 9. Formula for Mean Area method for finding out the quantity A. (A1+A2+A3) / 2 B. (A1+A2) / 3 C. (A1+A2) / 2 D. (A1+A2+A3) / 4 10 / 25 10. If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by A. Mid-section formula B. Trapezoidal formula C. Prismoidal formula D. All of the above 11 / 25 11. In general, while computing volume of earthwork, the volume computed by the prismoidal formula will be………………..as compared to that calculated by trapezoidal formula. A. smaller B. greater C. much smaller D. same 12 / 25 12. The assumption on which the trapezoidal formula for volumes is based, is A. The end sections are parallel planes. B. The mid-area of a pyramid is half the average area of the ends C. The volume of the prismoidal is over-es-timted and hence a prismoidal correction is applied. D. All of the above 13 / 25 13. Berms are provided in canals if these are A. fully in excavation B. partly in excavation and partly in embankment C. fully in embankment D. All of the above 14 / 25 14. Weight of 10 mm diameter rod per meter length is A. 0.39 kg B. 0.62 kg C. 0.89 kg D. 1.58 kg 15 / 25 15. Cross sectional area of 10 mm diameter rod is A. 28.274 B. 50.265 C. 78.540 D. 113.097 16 / 25 16. The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is A. L + 0.42 d B. L + 2 x 0.42 d C. L – 0.42 d D. L – 2 x 0.4 d 17 / 25 17. What should be the actual area of the length measuring 2.5cm * 4cm (0.025m * 0.04m) in a cadastral map drawn at a scale of 1:500? A. 150m² B. 250m² C. 350m² D. 450m² Explanation: Actual area = actual length * actual breadth = (0.025*500m) * (0.04*500m) = 250m² 18 / 25 18. The quantity of metal required in cubic metre for 3.7m wide road of one km long for one layer compacted thickness 8 cm is… A. 296 B. 444 C. 370 D. 222 Explanation: Quantity of metal (loose) = length * width * thickness = 1000m * 3.7m * 0.08m * 1.50 = 444 m3 [On compacting 12cm thickness, we get 8cm compacted thickness] 19 / 25 19. It is built-up covered area of a building measured by external dimension of the building at floor level is called A. floor area B. carpet area C. plinth area D. All of the above 20 / 25 20. Plinth area includes A. internal shafts greater than 2 m² area B. area of walls C. area of cantilever projection D. all of the above 21 / 25 21. Pick up the item of work not included in the plinth area estimate A. Wall thickness B. Room area C. Verandah area D. Courtyard area 22 / 25 22. The plinth area of a building not includes A. The plinth area of a building not includes B. area of stair cover C. lift and wall including landing D. area of cantilevered porch 23 / 25 23. Staircase, lifts etc are A. vertical circulation area B. horizontal circulation area C. both of above D. none of above 24 / 25 24. Floor area of verendhas, passages, corridors, stair cases etc which area used for movement of persons using the building is known as A. carpet area B. circulation area C. floor area D. plinth area 25 / 25 25. The floor area includes the area of the balcony up to A. 100% B. 75% C. 50% D. 25% Your score is The average score is 52% 0% Restart quiz Exit civil engineerEstimating & Costingmcqcivilnecupsc