247

Estimating & Costing Chapter Wise McQ Test of 25 Question #1

Estimating & Costing Chapter Wise McQ Test of 25 Question for PSC, NEC, UPSC, SSC and Many more.

1 / 25

1. The process of evaluating cost of construction of a project is called

2 / 25

2. Estimate is

3 / 25

3. Actual cost of structure is obtained

4 / 25

4. The essential requirements to prepare a good estimate are

5 / 25

5. To make out an estimate for a work the following data are necessary-Drawing, Specification and ___

6 / 25

6. To make out an estimate of a civil structure, we required

7 / 25

7. Estimate is

8 / 25

8. During the excavation of soil, some portion is left without disturbing, which is known as

9 / 25

9. Indicating works left in excavated trenches to facilitate the measurement of borrow pits are known as

10 / 25

10. The following item of earth work is not measured separately

11 / 25

11. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

12 / 25

12. A cement concrete road is 1000 m long, 8 m wide, and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is

13 / 25

13. For 2.5 cm C.C. floor for 100 sq metre of area, the quantity of cement concrete is

14 / 25

14. A layer of dry bricks put below the foundation concrete in the case of soft soils, is called

15 / 25

15. Quantity of a wall having length 10 m, height 2 m and thickness 20 cm is

16 / 25

16. Quantity of 6 metre long, 30 centimeter width and 3 metre high wall is:

17 / 25

17. The area of a segment of an arch with span l and riser r is approximately equal to

18 / 25

18. While estimating for plastering, usually no deduction is made for

19 / 25

19. What is the cost of plastering of 4 walls of a room with length 10m, breadth 5m and height 2.5m at the rate of Rs. 100 per sq.m?

20 / 25

20. Volume of steel in RCC work is

21 / 25

21. During estimate of RCC, the amount of steel deducted is

22 / 25

22. Pick up the incorrect statement from the following:

23 / 25

23. In measuring formwork, no deduction is made for opening upto

24 / 25

24. ________is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate.

25 / 25

25. The total estimated cost of a building electrification usually accounts for

Your score is

The average score is 62%

0%

Exit

Show CommentsClose Comments

Leave a comment